Location: 

Lowesoft

Objective: 

Deliver 30 PNs

Project Duration: 

Jan 2020 – Apr 2022 ( 16 months )

Members Deployed: 

9 operatives (~4 teams)

Project #1

Project Challenges: 

Working under 3 different contractors we had to deliver 30 PNs. Project was halted between Dec 2020 to June 2021 as Contractor1 went under liquidation.
We had to re-do all the PNs completed due to sub-standard quality of civils on the feeder route. All PNs had snags and had to be revisited. Civils was arranged by our contractors for this project.

Project Results: 

Working under 3 different contractors we delivered 28 PNs. Compensated for expected Project delays.

Location: 

Doncaster/Rotherham

Objective: 

Deliver 16 PNs

Project Duration: 

July 2020 – Sept 2020 ( 3 months )

Members Deployed: 

9 operatives (~4 teams)

Project #2

Project Challenges: 

Previous sub-contractors managed to deliver just 1 PN in 6 months, We were called in to replace them for speedy deployment.

Project Results: 

We managed to finish 16 PNs in a span of 3 months.

Location: 

Swindon

Objective: 

Deliver 10 PNs

Project Duration: 

Mar 2021 – July 2021 (4 months)

Members Deployed: 

7 operatives (~3 teams)

Project #3

Project Challenges: 

The project started in Sept2020, 1st sub-contractor was struggling to meet their targets, they completed 2 PNs in 6 months. We were contracted in March 2021 to help existing subcontractor meet target deadlines.

Project Results: 

We anticipated Civil delays and scheduled tasks accordingly, delivered 10 PNs in about 4 months

Location: 

Nottingham

Objective: 

Deliver 17 PNs

Project Duration: 

April 2022 – Sept 2022 ( 6 months )

Members Deployed: 

9 operatives (~4 teams)

Project #4

Project Challenges: 

Contractor struggled with high sub-contractor turnovers for the build, resulting in inefficient management, poor monitoring on builds and missed deadlines. We rescued the project by completing tasks before deadlines

Project Results: 

Delivered 17 PNs in 6 months working with different teams

Location: 

Bath

Objective: 

Deliver 17 PNs

Project Duration: 

Sept 2022 – Apr 2023 ( 8 months )

Members Deployed: 

8 operatives (~4 teams)

Project #5

Project Challenges: 

The Project started in Sept 2021 where they constructed 2 PNs and we took over from the existing sub-contractor in Sept2022 to deliver 17 PNs in a span of 7 months.

Project Results: 

NA

Location: 

London

Objective: 

Deliver 04 PNs

Project Duration: 

Feb 2024 – Apr 2024 ( 3 months )

Members Deployed: 

5 operatives (~2 teams)

Project #6

Project Challenges: 

Because of Industry recession & project funds being on hold, due to lack of ongoing work we partnered with existing subcontractor to deliver work for an ISP based in UK.

Project Results: 

NA

Location: 

Sheffield/Derby

Objective: 

Deliver 05 PNs

Project Duration: 

Apr 2024 – May 2024 ( 2 months )

Members Deployed: 

6 operatives (~3 teams)

Project #7

Project Challenges: 

We went in to help existing contractor to meet their deadlines on their projects

Project Results: 

NA

Location: 

Brighton

Objective: 

Deliver 05 PONs

Project Duration: 

Apr 2024 – May 2024 ( 2 months )

Members Deployed: 

4 operatives (~4 teams)

Project #8

Project Challenges: 

It was a short-term weekly contract work to delivers G-PONs for Openreach.

Project Results: 

NA

Location: 

Bowes Park

Objective: 

Spine Works

Project Duration: 

Apr 2024 – May 2024 ( 2 months )

Members Deployed: 

6 operatives (~3 teams)

Project #9

Project Challenges: 

Called for a rescue operation, 7 previous subcontractors failed to complete the task for 4 years. We delivered the subducts in 6 weeks.

Project Results: 

NA