Location:
Lowesoft
Objective:
Deliver 30 PNs
Project Duration:
Jan 2020 – Apr 2022 ( 16 months )
Members Deployed:
9 operatives (~4 teams)
Project Challenges:
Working under 3 different contractors we had to deliver 30 PNs. Project was halted between Dec 2020 to June 2021 as Contractor1 went under liquidation.
We had to re-do all the PNs completed due to sub-standard quality of civils on the feeder route. All PNs had snags and had to be revisited. Civils was arranged by our contractors for this project.
Project Results:
Working under 3 different contractors we delivered 28 PNs. Compensated for expected Project delays.
Location:
Doncaster/Rotherham
Objective:
Deliver 16 PNs
Project Duration:
July 2020 – Sept 2020 ( 3 months )
Members Deployed:
9 operatives (~4 teams)
Project Challenges:
Previous sub-contractors managed to deliver just 1 PN in 6 months, We were called in to replace them for speedy deployment.
Project Results:
We managed to finish 16 PNs in a span of 3 months.
Location:
Swindon
Objective:
Deliver 10 PNs
Project Duration:
Mar 2021 – July 2021 (4 months)
Members Deployed:
7 operatives (~3 teams)
Project Challenges:
The project started in Sept2020, 1st sub-contractor was struggling to meet their targets, they completed 2 PNs in 6 months. We were contracted in March 2021 to help existing subcontractor meet target deadlines.
Project Results:
We anticipated Civil delays and scheduled tasks accordingly, delivered 10 PNs in about 4 months
Location:
Nottingham
Objective:
Deliver 17 PNs
Project Duration:
April 2022 – Sept 2022 ( 6 months )
Members Deployed:
9 operatives (~4 teams)
Project Challenges:
Contractor struggled with high sub-contractor turnovers for the build, resulting in inefficient management, poor monitoring on builds and missed deadlines. We rescued the project by completing tasks before deadlines
Project Results:
Delivered 17 PNs in 6 months working with different teams
Location:
Bath
Objective:
Deliver 17 PNs
Project Duration:
Sept 2022 – Apr 2023 ( 8 months )
Members Deployed:
8 operatives (~4 teams)
Project Challenges:
The Project started in Sept 2021 where they constructed 2 PNs and we took over from the existing sub-contractor in Sept2022 to deliver 17 PNs in a span of 7 months.
Project Results:
NA
Location:
London
Objective:
Deliver 04 PNs
Project Duration:
Feb 2024 – Apr 2024 ( 3 months )
Members Deployed:
5 operatives (~2 teams)
Project Challenges:
Because of Industry recession & project funds being on hold, due to lack of ongoing work we partnered with existing subcontractor to deliver work for an ISP based in UK.
Project Results:
NA
Location:
Sheffield/Derby
Objective:
Deliver 05 PNs
Project Duration:
Apr 2024 – May 2024 ( 2 months )
Members Deployed:
6 operatives (~3 teams)
Project Challenges:
We went in to help existing contractor to meet their deadlines on their projects
Project Results:
NA
Location:
Brighton
Objective:
Deliver 05 PONs
Project Duration:
Apr 2024 – May 2024 ( 2 months )
Members Deployed:
4 operatives (~4 teams)
Project Challenges:
It was a short-term weekly contract work to delivers G-PONs for Openreach.
Project Results:
NA
Location:
Bowes Park
Objective:
Spine Works
Project Duration:
Apr 2024 – May 2024 ( 2 months )
Members Deployed:
6 operatives (~3 teams)
Project Challenges:
Called for a rescue operation, 7 previous subcontractors failed to complete the task for 4 years. We delivered the subducts in 6 weeks.
Project Results:
NA